Sabah Pan Borneo Highway Work Package 11 Gets Recovery Plan to Meet 2026 Deadline
Malaysia's Works Ministry has accepted a recovery plan from the contractor building Work Package 11 of the Sabah Pan Borneo Highway, aiming to complete the RM167.48 million project by September 2026 despite a current 32-day delay.